Print

Water Supply and Environmental Sanitation Project in Mongla Pourashava (2nd phase).

1Project Title Water Supply and Environmental Sanitation Project in Mongla Pourashava (2nd phase). 
2.a)Sponsoring Ministry/Division:Local Govt., Rural Development & Co operatives/Local Govt. Division
b)Executive Agency:Department of Public Health Engineering
    
3.Objectives of the Project: Expansion & rehabilitation of existing water supply infrastructures.
  Awareness building towards sustainable water supply.
  To increase the coverage of safe water supply services.
    
4.Project Period: July 2013- June 2015.
    
5.Cost of the Project:GOB: 195.582, PA:  0.00 & RPA:  0.00 million Tk
    
6.Project Location:Khulna_Mongla paurashava.
    
7.Main Components:Water Treatment plant construction, overhead tank construction, impounding reservoir construction.
 
Developed By Systech Digital Ltd.